Permit required Permits and bylaws · Checked on September 30, 2026

Heat pumps in Sainte-Anne-de-Bellevue: permits and bylaws

Planning a heat pump or an air conditioner in Sainte-Anne-de-Bellevue? Here is what the bylaws say: the permit, the distance from the lot lines, where the unit can go and the noise limit. It all comes from the official texts.

PermitPermit requiredCertificate of authorization required before installation
Fee$65Fee published by the city.
Distance from lot lines1 mAt least 1 m from the lot lines
Noise limit55 dBA55 dBA maximum, measured at the lot lines (zoning)
01 · Where the unit can go

Five spots, one answer for each.

Each answer is the bylaw rule, in short. “Not specified” means the text does not say: ask urban planning.

BackyardWith conditions

At least 1 m from the lot lines, hidden by an opaque screen or conifers.

Side yardWith conditions

At least 1 m from the lot lines, hidden by an opaque screen or conifers.

Front yardNot allowed

Not allowed in the front yard. Allowed in the secondary front yard of a corner lot, with a screen.

BalconyWith conditions

No higher than the railing, separated from the balcony by a screen and not visible from the street. 55 dBA maximum at the balcony’s edges.

Flat roofWith conditions

Building with 5 or more dwellings: no more than 3 m high, behind an opaque screen, not visible from the street. House: not provided for.

02 · Before the work

Good to know, and who to call.

Good to know

  • The certificate also covers moving a heat pump, generator or pool pump.
  • Include the certificate of location, a location plan and the unit’s spec sheet; 30-day processing once the file is complete.
  • New building with 5 or more dwellings: window air conditioners not allowed.
Who to call Urban planning department, 514 457-5720, mcrichlow@sadb.qc.ca Ask them to confirm the rules for your address before the work.
03 · Questions

The short answers.

Do you need a permit to install a heat pump in Sainte-Anne-de-Bellevue?

Certificate of authorization required before installation. Published fee: $65.

How far from the lot lines must the unit be?

At least 1 m from the lot lines.

Can a heat pump go in the front yard?

No. Not allowed in the front yard. Allowed in the secondary front yard of a corner lot, with a screen.

What is the noise limit?

55 dBA maximum, measured at the lot lines (zoning).

Who should I call to confirm before the work?

Urban planning department, 514 457-5720, mcrichlow@sadb.qc.ca.

04 · Sources

Read at the source.

Sources: Zoning bylaw 874, s. 124 (Table 5), 158, 159 and 160; 2026 tariffs bylaw 878, s. 2.1.1 l); permits and certificates bylaw 536; city “Mechanical equipment” form 2026 (administrative consolidation 2 of December 4, 2025 (874); 2026 tariffs (878)).

Checked by AirGreen on September 30, 2026.

This page is a summary. The official bylaw prevails. Confirm with the city before the work.

Compare the rules of other municipalities

AirGreen · Air conditioning and heating

A heat pump project in Sainte-Anne-de-Bellevue?

We come and see your property, and the estimate is free.

RBQ licence 5645-9605-01Subclasses 15.8, 15.10 and 16.
Free on-site estimate
Quote within 24 hours