Two systems in the same attic: why we did not connect the GREE FLEXX to the existing Unico network
At first glance, the project in Saint-Mathieu looked like an ordinary replacement. It was not. In the finished attic of this home in the Roussillon RCM, there was already a system: a Unico System Green Series, a small-duct high-velocity system installed years earlier to serve the upper floor without tearing into the ceilings. The owner contacted us for another reason: the main floor had never had anything other than electric baseboard heaters, and no central air conditioning.
The request was simple: add a central heat pump capable of heating and cooling the main part of the house without altering what was already working. This is exactly what is known as an “add-on” installation: the heat pump becomes the primary heating and cooling source, while the existing electric heating remains in place as backup for the coldest days.
We installed a GREE FLEXX R32, with the indoor unit configured as GUD24AH2/G-D(U) and the outdoor unit as GUD36W2/NhE-D(U).
The first assumption to rule out: connecting the new heat pump to the existing ducts
This is the request we receive every week, and it is also the first thing we ruled out here. The Unico system is a high-velocity system: it pushes air through small-diameter flexible ducts at a static pressure of approximately 1 to 2.5 in. w.c., which is several times the pressure for which a conventional central unit is designed. The blower in the FLEXX, like that of any residential central heat pump, operates within a much lower range.
Connecting the two would amount to asking a fan to push air through a duct network that was not designed for it. The consequences are predictable: collapsed airflow, a coil that freezes in cooling mode, repeated defrost cycles in heating mode, noise at the diffusers, and an electricity bill that rises instead of falling. A high-velocity system and a conventional system cannot be mixed—they can coexist.
So we used both systems side by side. The Unico Green Series remained in place on its concrete blocks, dedicated to the upper floor. The GREE FLEXX was installed next to it on its own support, with its own network of insulated ducts, its own drain, and its own thermostat. Two systems, two zones, two control strategies, in the same attic.
Why the GREE FLEXX R32 for this type of project
The FLEXX is a horizontal (side-discharge) airflow air handler, which matters enormously in an attic where the clearance beneath the roof slope is limited. A vertical unit would have required rebuilding the plenum and raising it beyond what the roof pitch allows.
Data for the selected unit:
- Indoor model: GUD24AH2/G-D(U) — 24,000 BTU/h rated cooling capacity, 23,000 BTU/h heating capacity
- Outdoor model: GUD36W2/NhE-D(U)
- True modulation: 12,000 to 30,000 BTU/h — the unit drops to half its rated capacity in mild weather and exceeds its rated capacity at peak demand
- Efficiency : 18 TRÉS2 (SEER2), 12.5 TRÉ2 (EER2), 10 CPSC2 (HSPF2)
- AHRI number : 217120759
- ENERGY STAR certification
- Heating range: down to -30 °C; cooling range: -15 °C to 54 °C
- R32 refrigerant, 2.5 lb factory charge, precharge covering 24.6 ft of piping
- Maximum piping length between units: 98.4 ft, maximum elevation difference 49.2 ft
- Diameters: 3/8 in liquid, 3/4 in gas
- 208–230 V power supply, 4.7 A MCA indoors, 27.7 A outdoors, 30 A MOCP
- Indoor unit dimensions: 18 1/8 x 43 1/2 x 21 1/4 in, 135.6 lb
- Conventional 24 VAC thermostat and factory-installed Wi-Fi
The most important consideration for a South Shore customer is not 18 TRÉS2. It is -30 °C. A heat pump that shuts down at -15 °C forces the auxiliary heating to operate during the most expensive weeks of winter. A heat pump that still produces heat at -25 °C or -28 °C postpones that changeover by several hundred hours per season, and that is where the real savings come from.
Sizing: why 24,000 BTU rather than 36,000
The temptation in a house this size is to go up a size “just to be sure.” This is the most common mistake with “add-on” installations.
We performed a room-by-room load calculation rather than following the rule of thumb. The main floor to be served, with its windows and partially upgraded original insulation, came in below 24,000 BTU/h at peak summer load. A 34,000 BTU/h unit would have operated in short cycles all summer: it would have reached the temperature setpoint quickly, shut off, and never run long enough to dehumidify. The classic result: a house at 22 °C that still feels clammy in July, in a municipality surrounded by farmland and drainage ditches where summer humidity is very real.
With a modulation range of 12,000 to 30,000 BTU/h, the 24,000 BTU/h FLEXX spends most of the season running at low output, in long cycles, while retaining reserve capacity for heat waves and winter nights.
The installation process, from support to startup
The support and service access
The indoor unit rests on solid, level concrete blocks, with a slight slope toward the drain connection. This tedious detail is what saves floors: equipment installed crookedly in an attic sends condensation water over the edge of the pan instead of into the drain.
We also preserved service clearance in front of the electrical panel and the access door to the coil. An attic is where technicians work least comfortably; the person who installs the equipment determines what the person maintaining it will experience over the next fifteen years.
The ducts
The new duct run branches laterally from the unit into a large-diameter insulated flexible trunk, then divides toward the main-floor drops. Three rules we systematically follow in an attic:
- Flexible duct is pulled taut, never compressed. A sagging flexible duct loses a significant portion of its airflow and creates low points where moisture accumulates.
- Bend radii are maintained from the very start at the collar. A tight elbow placed directly against the unit costs more in pressure drop than three metres of straight duct.
- The duct insulation must remain on the warm side of the enclosure. A poorly insulated cold duct in a ventilated attic causes condensation in the insulation, followed by a ceiling stain in August.
Condensate
The unit’s drain connection slopes down through flexible corrugated hose to a PVC system equipped with an accessible U-shaped trap and cleanout plugs. A float safety switch was added: if the drain becomes clogged, the system shuts down instead of overflowing into the ceiling.
A poorly made trap is the most common cause of water damage with an attic air handler. Without a trap, the blower’s negative pressure holds water in the pan. With a trap that is too short, it loses its prime. We prime it with water at startup and show the customer where the plugs are for annual maintenance.
The R32 refrigeration circuit
The 3/8 in. and 3/4 in. piping was brazed under nitrogen, then evacuated to a deep vacuum, with a pressure-rise test performed before opening the valves. The run remained within the factory charge length, so no additional refrigerant was needed—but we systematically document the actual length in the file because that is the information the manufacturer requests in the event of a claim.
The A2L leak detection sensor: the detail many people still overlook
R32 is a refrigerant classified as A2L, meaning it is mildly flammable. The FLEXX comes with an integrated leak detection sensor, and the label affixed to the unit’s panel is explicit: the sensor’s position depends on the air discharge direction. On a horizontal-flow unit that can be configured for left- or right-hand operation, an on-site conversion without repositioning the sensor renders the protection ineffective.
We check this point during every commissioning and test the associated shutdown logic. This is a new aspect for many installers in Quebec, and it is precisely the kind of detail that an inspector or insurer will examine in the coming years.
Power supply and controls
A dedicated circuit compliant with the outdoor-side 30 A MOCP, a disconnect within sight, 24 V wiring to a conventional thermostat, and a Wi-Fi connection. The upper floor retains its own Unico control. The two systems do not conflict because each regulates its own zone.
What this project teaches homeowners in Saint-Mathieu, La Prairie, Candiac, and Delson
The most common mistakes with a central “add-on” heat pump
- Reusing an incompatible duct network simply because it is already there. A high-velocity, undersized, or leaky duct network negates the efficiency stated on the technical data sheet.
- Oversizing. An oversized heat pump costs more to purchase, dehumidifies less effectively, and wears out faster.
- Forgetting the changeover to auxiliary heat. On an “add-on” system, the transition logic between the heat pump and the existing electric heating must be set up and verified. If configured incorrectly, it runs the baseboards at the same time as the heat pump, causing the bill to skyrocket.
- Neglecting the outdoor unit in winter. A unit installed too low disappears under the snow and becomes an ice-covered box again. We elevate it on a support and keep the defrost drainage clear.
- Failing to document commissioning. Without records of the pressures, temperatures, airflow, and AHRI number, a subsidy application becomes a weak case.
Subsidies: the state of things in 2026
Two important changes for homeowners on the South Shore:
- The Chauffez vert program ended on March 31, 2026. In any case, it only covered the conversion of oil or propane systems.
- Hydro-Québec's LogisVert program remains the main incentive for a central heat pump. The key conditions are: being a Hydro-Québec customer, having the work carried out by a contractor holding a RBQ licence and registered with the program, installing an ENERGY STAR certified unit with a valid AHRI number, and submitting the application within the months following the invoice. The incentive is paid as a rebate after the fact.
The number one reason for rejection that we see is not the model: it is a missing AHRI number or one that does not match the indoor/outdoor combination actually installed. The FLEXX in the GUD24AH2/G-D(U) + GUD36W2/NhE-D(U) configuration bears the 217120759 number, which is included in the file provided to the client. Amounts vary depending on the unit and configuration; we validate them before signing rather than afterward.
The Rénoclimat program may also apply when other energy-efficiency work is carried out at the same time.
Why homeowners in the Roussillon RCM call us
We install central heat pumps, wall-mounted heat pumps, mini-split systems, air conditioners, and heat-recovery ventilators throughout Montreal, Laval, Longueuil, the North Shore, and the South Shore, including smaller municipalities in Montérégie that many contractors avoid. Saint-Mathieu is one of them.
What this project illustrates: the value does not come from the model selected; it comes from assessing the building before the purchase. A low attic, an existing high-velocity system, a ground floor with baseboard heating, and a clearance constraint—each of these factors could have turned a good machine into a disappointing installation.
If you are considering a central add-on heat pump, replacing a central unit, or adding air conditioning to a home that has never had it, write to us or call us. We travel to your location, take measurements, calculate the load, and provide you with a clear proposal including the AHRI number, actual efficiency ratings, and eligibility for available rebates, already verified.
AirGreen — Air Conditioning & Heating. RBQ 5645-9605-01.
The job tools
Two quick checks with real numbers: what heat costs, and what your current heaters add up to in BTU/h.
Conversion: 1 W = 3.412 BTU/h. An indication, not a load calculation: baseboards and furnaces are often stronger than the real need, and they can stay as backup. AirGreen confirms the capacity on site.
How the job unfolds
The main steps of this kind of job at AirGreen. Every house has its quirks: the estimate brings them out.
We look at the ducts, the current indoor module, the electrical panel and the planned spot for the outdoor unit.
The equipment combination, capacity and price, in writing. We check whether the combination qualifies for assistance programs.
Access protected, old unit disconnected and removed when it is being replaced.
Electric furnace or air handler, with its coil, connected to the supply and return ducts.
On a level base, raised above the snow, with free space all around.
Insulated, they enter through a sealed opening and run to the indoor coil.
Dedicated circuits, accessible disconnect, a thermostat that works with the heat pump and the backup heat.
Leak test, vacuum, start-up, airflow check and a test of both modes.
Filter, thermostat, backup heat in extreme cold: what to know before winter.
- The on-site estimateWe look at the ducts, the current indoor module, the electrical panel and the planned spot for the outdoor unit.
- The quoteThe equipment combination, capacity and price, in writing. We check whether the combination qualifies for assistance programs.
- Getting readyAccess protected, old unit disconnected and removed when it is being replaced.
- The indoor moduleElectric furnace or air handler, with its coil, connected to the supply and return ducts.
- The outdoor unitOn a level base, raised above the snow, with free space all around.
- The refrigerant linesInsulated, they enter through a sealed opening and run to the indoor coil.
- Electrical and thermostatDedicated circuits, accessible disconnect, a thermostat that works with the heat pump and the backup heat.
- Tests and start-upLeak test, vacuum, start-up, airflow check and a test of both modes.
- The walkthroughFilter, thermostat, backup heat in extreme cold: what to know before winter.
What we check on a job like this one
Each number is a point we check on site. Switch between summer and winter to watch air and heat move.
In summer, the outdoor unit rejects the house's heat outside.
Generic illustration of this type of installation, not a survey of this job site. Tap a number.
It captures or rejects heat outside. It sits on a level base, above the snow, with free space all around.
The insulated refrigerant lines enter the house through a sealed opening and run to the indoor coil.
A shut-off switch near the outdoor unit isolates it safely for service.
Sitting on the indoor module, it moves heat between the house air and the refrigerant.
Electric furnace or air handler: its fan pushes air through the ducts. The electric backup takes over in extreme cold.
Supply ducts bring air to the rooms; returns bring it back to the unit. Their condition matters as much as the unit's.
It protects the coil and the fan. A dirty filter cuts airflow, so it gets checked regularly.
It runs the heat pump and the backup heat. It must be compatible with the installed system.
Is your home ready?
Check what applies at your place. A "no" is not a refusal: it is what we sort out during the estimate.
Good habits, once the unit is in place
Six simple habits that keep the unit going. Your list stays on this device.
What to do, season by season
Three habits per season for this unit. They take a few minutes and prevent many calls.
- Check the indoor module's filter.
- Clear winter debris from the outdoor unit.
- Test cooling before the heat arrives.
- Check the filter more often in peak season.
- Keep registers and returns clear.
- Watch condensate drainage near the coil.
- Change or clean the filter.
- Test heating and backup heat before the cold.
- Book periodic maintenance.
- Clear snow around the outdoor unit.
- Store nothing in front of the indoor module.
- Note any unusual noise or smell and call us.
The right pages, at the right time
Four statements: true or false?
It all comes down to details you have just seen.
1. A central heat pump uses the house's ducts.
It connects to the existing ducts to heat and cool everywhere.
2. In extreme cold, electric backup heat can take over.
The indoor module (furnace or air handler) works with the heat pump and takes over in extreme cold.
3. The filter only gets changed when the unit breaks down.
A dirty filter cuts airflow. It gets checked regularly.
4. You can reuse the old unit's size without checking.
The house may have changed: insulation, windows, added rooms. Capacity is confirmed on site.
0 / 4 right answers
What people ask us about this kind of work
Can I keep my current ducts?
What happens in extreme cold?
Furnace, air handler, ducted: what is the difference?
Are there grants?
Do I need a permit?
How much can I save?
How is the LogisVert assistance calculated?
Will my current thermostat work?
Central or wall units: which one?
Does AirGreen hold the required licences?
Is the estimate free?
No question matches. Write to us: we answer.
More jobs to see, near you
By town, by equipment or by region: browse more than 4,700 published projects.
Each dot: a town where AirGreen has published projects. The glowing dot: this job.
An on-site estimate, the right capacity, the right equipment.
The on-site estimate is free and the quote follows within 24 hours.
Text and photo: a real AirGreen Climatisation & Chauffage job. The diagrams are generic illustrations of the type of installation, not a survey of this job site. Sources of the added figures: airgreen.ca product pages (NEEP / AHRI performance), Hydro-Québec (Heat pumps page, LogisVert, read on 13 October 2026), Régie de l’énergie (rate D as of 1 April 2026).