Heat pumps in Otterburn Park: permits and bylaws
Planning a heat pump or an air conditioner in Otterburn Park? Here is what the bylaws say: the permit, the distance from the lot lines, where the unit can go and the noise limit. It all comes from the official texts.

Five spots, one answer for each.
Each answer is the bylaw rule, in short. “Not specified” means the text does not say: ask urban planning.
At least 2 m from the lot lines, hidden from the street by a dense hedge, landscaping, an opaque fence or the house.
At least 2 m from the lot lines, hidden from the street by a dense hedge, landscaping, an opaque fence or the house.
Not allowed in the front yard of a 1- to 3-unit home (allowed for buildings with 4 or more units or community housing).
Multi-family building: allowed on a balcony if no higher than the guardrail; no screen needed.
Not specified in the bylaw: confirm with urban planning.
Good to know, and who to call.
Good to know
- Corner lot: allowed in the secondary front yard, except in front of the house, 2 m from the lot lines and hidden from the street.
- Multi-family building: no unit on the main façade above the ground floor, except on a balcony.
- Some areas are subject to a PIIA (architectural review): check before installing.
The short answers.
Do you need a permit to install a heat pump in Otterburn Park?
No permit required (City’s official permit list).
How far from the lot lines must the unit be?
At least 2 m from the lot lines.
Can a heat pump go in the front yard?
No. Not allowed in the front yard of a 1- to 3-unit home (allowed for buildings with 4 or more units or community housing).
What is the noise limit?
55 dBA from 7 a.m. to 10 p.m., 50 dBA from 10 p.m. to 7 a.m.: maximum.
Who should I call to confirm before the work?
Technical services (urban planning), 120 Bellevue St.; City Hall, 450 536-0303, info@opark.ca.
Read at the source.
Sources: City 2026 permit and fee list; zoning bylaw 431, s. 89 (table 6, line 22); City “Règlements municipaux – Thermopompe” page (zoning: consolidated December 10, 2025; 2026 permit list; checked September 30, 2026).
Checked by AirGreen on September 30, 2026.
This page is a summary. The official bylaw prevails. Confirm with the city before the work.
A heat pump project in Otterburn Park?
We come and see your property, and the estimate is free.